PRO-FLOAT for Watermain
The PRO-FLOAT system has been used at a crossing at Lismore Scotland
from the main land to the Island of Lismore.
The watermain has been protected over the full 1200 meter with Pro-Pipes.
Preparation time by company Caldive from Invergordon (Scotland) was
approx. 1 week.
Installing the pipes including the out-float and sinking proces 1 day.
The watermain, protected over the full 1200 meter.
Installing the Pro-pipe including floating it out offshore has taken 1
day.
Digging a ditch to lay the PRO-FLOAT line in for a better swimm out effect.
Floating in position.
A simple tugboat can do the job.